Freudenberg IT

Data Center and Tenant Improvements

Freudenberg IT’s Data Center and Tenant Improvements project was completed in two phases. Phase One involved a 10,000 sf tenant up-fit. Phase Two consisted of an 80,000 sf data center complex including a 6,000 sf data center, a 2,000 sf mechanical/electrical room, and an emergency generator service yard. Electrical and mechanical systems were constructed with N+1 redundancy generators and a  one megawatt UPS system was installed. The CRAC system included rooftop mounted chillers, a mechanical room mounted CRAC, and all related distribution ductwork. The data center was built with a 4-hour fire rating.

  • Service — General Contracting
  • Architect — Integrated Design | Stantec