One of BE&K Building Group’s first projects for Pfizer at this location provided for a 3,000 sf expansion to their existing facility. We also converted an existing 1,400 sf office area into a quality control/quality assurance laboratory. Designed as a Class 100,000 clean room, the project included tie-ins to the existing plant’s clean-steam system for the new HVAC system. Later, we designed and built a 30,000 sf two-story building addition to house maintenance, calibration, parts, equipment storage, high-density document storage, and a data center. UPS and generator systems were installed to provide emergency power supply for servers, CRAC units, and lighting. A 13,000 sf two-story building addition was also provided that included locker rooms, restrooms, showers, uniform storage, visitors area, offices, security, site services, and maintenance.

  • Service — Design-Build
  • Architects — O'Neal | O'Brien Atkins | BE&K
  • Repeat Client